The Sungnam-Yeoju City Railway Project No.2 is a section of railway tunnel located in the City of Sungnam, South Korea. The project included the excavation of 2.9 km’s of tunnel length.

A 165m section of the tunnel length passes below residential buildings area at an average depth of 32m. For this section of tunnel excavation authorities have set a strict environmental limit on ground vibration.

Fines Control to Improve Copper Leaching Recovery
13/05/2011

Carmen de Andacollo is located in Region IV in central Chile at an elevation of 1,000 metres, approximately 350 kilometres north of Santiago and 100 km from La Serena City, near the southern limit of the Atacama Desert Andacollo is an open cut copper mine that produces copper cathode through leaching operations.

Maximising Coal Recovery Under High Voltage Power Lines
13/05/2011

Khanyisa Colliery is situated approximately 10km from the Kendal power station, in Mpumalanga province, South Africa.

The mine is operated by Wescoal Holdings Limited. Wescoal successfully diversified into the mining of coal through the acquisition of the Khanyisa Mine at Kendal in Mpumalanga during 2009. Production commenced and the first coal was extracted immediately. The extracted coal is supplied for the consumption of the power station.

A drill and blast company, Dyna Drilling, is sub-contracted by Khanyisa to provide drilling and blasting operations.

Reducing Vibration near Critical Structures in Development Tunnelling
13/05/2011

Mining Technologies International (MTI) is one of Canada’s largest manufacturers and suppliers of mining equipment, MTI has constructed its own test tunnel on the west side of Sudbury Ontario at their Magill Street property. A natural rock outcrop provided the perfect spot to build a decline that will be extended underground to test its products in an actual working environment. The decline extends at a 15-per-cent grade. It is a 5.2-by-5.2-metre tunnel, the standard dimension of most Sudbury mines.

MTI has created a high profile project for local Mining Companies and suppliers to test and showcase their newly designed mine equipment and new technologies from various suppliers including Orica in an actual underground environment.

Increasing Construction productivity through risk management and technology
09/05/2011

Orica Mining Service’s expertise in controlled blasting technology was called upon by the project leaders, Thiess John Holland (TJH), to clear large areas of rock which was too hard for mechanical rock breakers to work efficiently.

TJH sought Orica’s advice to come up with a solution to excavate 30,000 cubic metres of hard massive volcanic tuff from the site of a critical tunnel portal, right next to a major arterial road, heritage listed buildings, a church and a three story office building.